We're excited to announce new developments happening with the Rotary Centennial Park! We'll keep a running update on new developments as they unfold, photos, videos and other media so you can watch the transformation from lot to beautiful park! Stay up-to-date by checking back here periodically!
We are beginning construction as soon as the first week of March! Here is a rough schedule of activities:
Preparation for Groundbreaking: March
• Clearing lot weeds and trees
• Preparation for perimeter tree planting
• Water hookup and irrigation start
Groundbreaking: Summer 2020
• Rotary workday includes planting of 24 large trees, sign installation and irrigation connection
Project out to public bid: Summer 2020
Bid awarded: Late Summer 2020
Construction begins: Fall 2020
Project completion: Spring 2021
This is the final design for Rotary Centennial Park! Some of the amazing features are:
• A multi-use turf field
• Childrens play area
• Multiple areas with shaded picnic tables and structures
• Basketball court
Transformation!
Empty Lot > Graded Lot
Graded Lot > Sidewalk Additions